Project Status - Farnborough, England - 29th August 1997

Black Rock Fund Raising: 65.99% Complete

Internet Fuel Campaign: 92.15% Complete

The ThrustSSC Team are preparing for departure to the Black Rock Desert, Nevada, USA on Tuesday, September 2nd 1997. Funds are still desperately short - please see "It's Time To Stand Up And Be Counted" for more details.


Microplex Web Cameras

The very latest status of the car can normally be seen through the live pictures from our Microplex Web Cameras. The Web Cameras are currently offline and have been packed for transit to America.


Individual Status Reports

Car

  1. The car is ready to be loaded for transit to America for the record attempt

Team

  1. The ThrustSSC Team are packing for Black Rock
  2. Andrew Noble is in Gerlach preparing for the team's arrival

Equipment

  1. Equipment is being packed for Black Rock at the project's old base at P8.R Shed, DRA, Farnborough
  2. All equipment not required for Black Rock has been moved to the project's new base at X1 Shed

Black Rock Desert, Nevada, USA

  1. Permits to use the desert have been delayed until 6th September
  2. Andrew Noble is on site preparing for the team's arrival at the end of August
  3. The desert is dry for some 15 miles and the 13-mile course is good

Web Site

  1. Most of the Web Site equipment is now packed for transit
  2. Accesses are currently running around 340,000 a week

Jeremy Duck...

... has found a nice warm cardboard box to nest in for the trip to America. He hasn't had a bath, though.


Plans

Please check our Runs Database for the very latest information on the progress of ThrustSSC - the database is always updated as soon as possible after the car runs - and always before any report is written and published.