Project Status - Farnborough, England - 17th August 1997
Black Rock Fund Raising: 32.31% Complete (at close of play on 15th August)
Microplex Web Cameras
The very latest status of the car can be seen through the live pictures from our
Microplex Web Cameras.
Individual Status Reports
Car
- The car has completed runway tests prior to Black Rock
- The resonance tests have been completed and have revealed a wealth of useful data
Team
- The ThrustSSC Team are hard at work preparing for Black Rock
- Andrew Noble is in Gerlach making preparations for the team's arrival
Equipment
- All the equipment has now been cleaned, checked and prepared for further use
- Equipment is being packed for Black Rock
Black Rock Desert, Nevada, USA
- Permits to use the desert have been delayed until 6th September. The team will depart for America on the evening of 1st September.
- Andrew Noble is on site preparing for the team's arrival at the end of August
- The desert is dry for some 15 miles and the 13-mile course is good
Web Site
- Accesses are currently running around 286,000 a week
- The backlog of background information for the Web Site is slowly being cleared
Jeremy Duck...
... is pondering (pun intended) a return to the workshop end of P8R Shed.
Plans
- Car
- Prepare for transit to America
- Equipment
- Pack and prepare for transit to America
- Black Rock Desert
- Continue track preparations
- Web Site
- Continue to work through the backlog...
- Prepare for the Black Rock Campaign reporting
Please check our Runs Database for the very latest information
on the progress of ThrustSSC - the database is always updated as soon as possible after the car runs - and always before any
report is written and published.