Project Status - Al Jafr, Jordan - 27th November 1996

Car

A further run on Thursday revealed modifications required to the steering for the high-speed desert environment. Parts from the UK have arrived and are being fitted.

Please check our Runs Database for the very latest information on the progress of ThrustSSC - the database is always updated as soon as possible after the car runs - and always before any report is written and published.

Desert

Although untouched by a severe overnight thunderstorm which brought heavy rain to the Al Jafr airbase and surrounding area, yesterday morning the team found advancing flood-water approaching the access track and Desert Pits at a rate of a foot a second. The entire desert site has been evacuated as a precaution until the desert has absorbed the water.

Tracks 17, 16 (part) and 15 have been used so far.

Desert Pits

Due to the flooding, the Desert Pits is currently evacuated.

Weather

(0800hrs) Today started gloomy, but is now brightening up.

(1700hrs) After a bright day, thunderstorms are now approaching Al Jafr again.